Imgs AL MUFTAH TOWER (2B+G+14 OFFICE BUILDING)

Building Nature:

  • Image

    This project is an office building located at West Bay in Doha. This consists of fifteen floors; each floor consists of more than five offices

HVAC System Description:

  • Image

    The HVAC system in the building is a central air condition system (chilled water cooling system). Each room is served by one fan coil unit. The fan coil units are connected to one treated fresh air handling units. The exhaust air system extract from the building by using energy recovery unit

  • Image

    The HVAC system includes the following items: - 80 FCU's - 10 AHU's - 10 FANS - 03 CHILLERS - 06 PUMPS - 100 VALVES

GTC scope of work:

  • Image

    Testing and balancing for all HVAC system

  • Image

    Handling the system to the client

Contractor:

  • Image

    UCC